At a glance

Item typeWhy it can set the date (the process, not a period)Sign off firstAsk the maker
Natural stone (tops, slabs, flooring)Chosen from quarry or slab stock, and often templated on site before it is cut.Slab or range selection; site template or survey; shop drawing.When the slab is reserved; when the template is needed; who stores it.
Made-to-order glass lightingMade to order on the glassmaker’s own schedule (our lead times page: Murano glass is blown to order).Glass colour sample; shop drawing; electrical specification.What is needed to book a production slot.
Hand-finished or patinated metalFinishing and curing are not compressed (our lead times page).Finish sample and batch approval; shop drawing.How the finish is batched, and what can run in parallel.
Bespoke ironmongeryMade and finished to order.Hardware schedule; finish sample.Whether a sample piece comes before the run.
COM fabric or leatherMills have their own queues (our lead times page). The fire test covers cover, filling and interliner together, so settle the cover first.Cover approved; width and yardage; fire evidence; batch.Whether the cover can be held against the batch.
Matched veneerLeaves for a matched run are chosen and kept in sequence from one log (our reading).Flitch or sample approval; set-out drawing.How the flitch is reserved.
Repeated items that need a prototypeProduction cannot be released until the prototype is signed.Prototype or first article approved.When the prototype review falls in the programme.

Illustrative, not a forecast. No period is given because each belongs to the piece, the workshop and the date. Stone, glass, ironmongery and COM are on our lead times page’s long-lead list; the other rows are our reading.

Early package or main package

Designing Buildings defines a long lead-time item as one where the period between order and delivery is long enough to harm the project, or long enough that it has to be ordered well in advance (page last edited 23 January 2021). It adds that such items are sometimes ordered before contractors are appointed so that they do not delay the programme, and that components with long lead times often need approved production drawings before they can be ordered. That last point is what this sheet is built on: ordering early moves the design deadline forward. A group of such items bought ahead of the main contract is an early procurement package.

Whether early ordering is open to you depends on the route. Where the client or an agent places the orders, items can be bought ahead of the main contract: BIID notes that specialist items such as curtains, art, rugs, freestanding furniture and light fittings may be left out of the main contract, and Designing Buildings says FF&E may be procured separately, with each element’s contract defined clearly. Inside a contractor’s package, early orders are possible if the contract provides for them. The RIBA Plan of Work 2020 Overview describes packages for crucial building systems being tendered and awarded earlier in Stage 4 under management contracting (PDF page 92), and a contractor being appointed under a pre-contract services agreement so that some work can start before the contract sum is settled (PDF page 93). See FF&E procurement routes compared, and ask the project’s contract adviser which applies.

Three questions decide whether an item goes early or stays in the main package. If the answer to any is no, either close the gap or keep the item in the main package.

Early package or main package: three questions an item must passA flow from left to right. An item from the FF&E schedule goes to the first question: does its order date set the date it is needed on site? Then the second: are its shop drawing and control sample signed? Then the third: can the order be made and held safely, meaning storage, change and payment? A yes to all three leads to the early package, where the item is ordered against the signed drawing. A no to any question leads down to a wide box that says main package, or close the gap and ask again. A band at the foot says that either way the item goes in the long-lead register with its latest order date.Item on theFF&EscheduleDoes its orderdate set the dateit is needed?Are its drawingand control samplesigned?Can the order bemade and heldsafely?YesYesYesEarly package:order againstthe signeddrawingNoNoNoMain package, or close the gap and ask againEither way, the item goes in the long-lead register with its latest order date.
Early package or main package: three questions. Our practice reading, not a standard. Original drawing by Make Bespoke Studio.

What an early order commits you to

An early order commits money and a production slot against a design that has not yet been built. If the design changes afterwards, something already ordered may have to be reworked or scrapped. Our pricing page says that once a quotation is approved and the deposit paid, the price is fixed for the agreed scope, and a later variation is costed and approved in writing before work changes. What an early order commits, whether a deposit is needed, and what can still change after it is placed are agreed with the maker for each case. This sheet states no terms.

Our lead times page says we flag long-lead components in the first programme so that they are ordered against drawing approval, not discovered late, and that the clock is counted from written approval of the shop drawings and samples. Our hospitality FF&E page says prototypes and long-lead items are started early. The point of both is the same as the test above: order early, but only against something signed.

What must be signed off first

Eight gates sit in front of an early order. Not every item needs all of them, but an item that skips one should do so knowingly, and the register records which gates are still open.

Sign off firstWhy it must come firstRead more
Shop drawing approved, revision namedDesigning Buildings notes that long-lead components often need approved production drawings before they can be ordered. The order should cite the revision.Shop drawing approval checklist
Control sample signedIt is the benchmark the item is made and checked against. Ordering before it is signed means ordering against a guess.Sample hierarchy and approval
Site dimensions set, where the item depends on themFitted pieces are made to measured sizes, so the survey comes first.Site survey and dimension verification
Quantity and variants fixedA changed quantity or variant is a changed order.FF&E schedule template
Evidence requirements agreed: fire, timber, testsA test report applies to the item that was tested, so settle the build before the order.Fire documentation matrix
Delivery route, storage and site readinessAn early item may arrive well before the site is ready for it.Delivery access survey; site readiness checklist
Who may commit, and which contract the order sits inThe procurement route decides who places the order and who pays.FF&E procurement routes compared
How a change will be handled after the orderA substitution after an order carries cost and needs a record.Substitution register

Working out the latest order date without guessing a duration

The latest order date is a sum, worked backwards from the date the item is needed in the room. Each term of the sum is a period that only the maker can give, and a period means nothing without the event it is counted from. Our lead times page counts its clock from written approval of the shop drawings and samples; another maker may count from the order or from the deposit. Write the event next to every period.

  1. Start from the date needed on site, taken from the programme.
  2. Take away the delivery window, to the address and floor, as the maker gives it.
  3. Take away the making period, as the maker gives it, with the event it starts from.
  4. Take away the approvals still to come, including your own time to review and the maker’s time to revise.
  5. Allow storage or float, so that a slipped date does not become a missed one.
  6. Re-run the sum whenever a sign-off date or a maker’s period changes.

If no maker has given a period yet, write ‘ask’ in the register. An estimate copied from another job looks like a fact and is not one.

Working back from the date needed on site to the latest order dateA horizontal bar made of four consecutive blocks, left to right: approvals still to come, making period, delivery window, and storage or float. Its right end is marked as the date needed on site. Its left end, where the first block begins, is marked as the latest order date. An arrow under the bar runs right to left to show the order of the sum: start from the date needed, take away each block, and the date you reach is the latest order date. Each block is a period given by the maker, with the event it is counted from. The blocks are equal in the drawing and are not to scale; no period is stated.Not to scale. Each block is a period the maker gives, with the event it starts from.Approvalsstill to comeMakingperiodDeliverywindowStorageor floatLatestorder dateDate neededon siteStart at the date needed, take away each block, and the date you reach is the latest order date.
Working back from the date needed on site to the latest order date. Not to scale; no period is stated. Original drawing by Make Bespoke Studio.

The long-lead register

The register is a short list, issued with the FF&E schedule and reviewed at every programme meeting. It carries one line for each item that passed the first question of the test, whether or not it is ordered early. The columns:

ColumnWhat to enterExample (replace)
RefA reference for the register line.[L-01]
Item, codeThe item code from the FF&E schedule, never a new one.[B-07]
Why long-leadThe process that sets the date, in a few words.[Slab chosen, site template]
Sign off firstThe gates from the table above that apply, with their status.[Drawing rev C approved; survey open]
Maker’s periodThe period the maker gives, with the event it is counted from. Write ‘ask’ until the maker has said.[ ] from [written approval of drawing and sample]
Needed on siteThe date the item is needed in the room, from the programme.[date]
Latest orderCalculated: needed on site, less delivery window, making period and approvals still to come.[date]
Status, ownerOne value from the FF&E schedule’s status list, and a named person.[Not ordered], [name]
RiskWhat could make it late: an approval, a selection, a survey, a shipping step.[Template not yet booked]

Keep one register and one owner. A register that is not reviewed when a date moves is only a list. See the FF&E schedule template for the status list it shares, and where bespoke work sits in the RIBA Plan of Work for when each sign-off falls.

The long-lead register as a form: item, why long-lead, what to sign off first, maker's period, dates, statusA drawn form headed Long-lead register, with placeholders for project, register revision and date. A table has eight columns: reference, item and code, why it is long-lead, what to sign off first, the maker's period, the date needed on site, the latest order date, and status with owner. Three example rows are filled with placeholders in square brackets: a stone top, a glass light and a fabric supplied by the designer. Beneath the table a green band gives the sum for the latest order date: date needed on site, less the delivery window, the making period and the approvals still to come, each given by the maker with the event it is counted from. No period is stated.LONG-LEAD REGISTERProject [ ] Register rev [ ] Date [ ]RefItem, codeWhy long-leadSign off firstMaker's periodNeeded on siteLatest orderStatus, ownerL-01Stone top[item code]Slab chosen,site templateDrawing rev [ ];survey [ref][ ] from[event][date][date][Not ordered][owner]L-02Glass light[item code]Made to order,maker's slotDrawing; glasscolour sample[ ] from[event][date][date][Ordered][owner]L-03COM fabric[item code]Mill queue,batchCover approved;fire report[ ] from[event][date][date][Quoted][owner]Latest order = needed on site, less delivery window, making period and approvals still to come (each from the maker).
The long-lead register as a form, with three placeholder lines. Original drawing by Make Bespoke Studio.

Specification wording

Paste into your schedule or specification and replace anything in [square brackets] with your own figures. Wording is a starting point: your specification governs.

Early procurement package (note for tender documents)
The Employer intends to place early orders for the items in Schedule [ref] ahead of the Building Contract, under [separate contracts with the suppliers / a pre-contract services agreement / the Contractor's early works order]. The Contractor is to allow for receiving, unloading, storing and protecting these items, for [installing / coordinating the installation of] them, and for the builder's work, fixings, power, data and access they depend on, as Schedule [ref]. The programme assumes the items are on site by [date]. [Late delivery of early-ordered items is / is not] a Contractor risk event: clause [ref].
Conditions for an early order
An item in Schedule [ref] is ordered early only when: shop drawing [number, revision] is approved; control sample [S-nn] is signed; site dimensions are confirmed [survey ref] where the item depends on them; evidence requirements [fire, timber, tests] are agreed; the maker has confirmed in writing what is committed by the order, what may still change and at what effect on cost and programme, and where the item is stored, by whom and insured by whom; and [named role] has authorised the commitment. The order names the drawing revision and the sample reference.
Long-lead register
The long-lead register is held by [party] at revision [letter] and issued with the FF&E schedule. For each item it records the maker's period and the event it is counted from, the date needed on site, the latest order date calculated from them, what must be signed off first, status and owner, and the risk to the date. It is reviewed at each [programme meeting] and whenever a sign-off date changes.
Request to the maker
For [item] please confirm: (1) the approvals you need and the time you need to review them after submission; (2) your making period and the event it is counted from; (3) your delivery window to [address]; (4) what you need in order to commit materials or a production slot, and what is committed once ordered; (5) storage arrangements if the site is not ready; (6) anything that could lengthen these. Give each period with its start event, not as a single figure.

Terms used on this page

Long-lead item
An item whose making and delivery takes long enough that its order date drives the project programme, so it has to be ordered earlier than the rest. Typical examples are hand-finished, imported or custom-made pieces.
Early procurement package
A group of long-lead items bought ahead of the main contract, usually under a separate order, so they arrive when needed. It requires design and samples to be settled sooner.

All specification and delivery terms

Standards and sources

Questions we are asked

What is a long-lead item?

One whose making and delivery take long enough that its order date drives the programme. Designing Buildings describes it as an item where the period from order to delivery is long enough to harm the project or to need ordering well in advance. In FF&E the usual suspects are items made to order by a third party, items chosen from natural stock, hand finishing, and anything that needs a prototype first.

Which FF&E items should be ordered early?

Those that pass three tests: the order date, not the making, will set the date the item is needed; the drawing and control sample are signed; and the order can be held safely, meaning storage, change and payment are settled. Stone, made-to-order glass lighting, hand-finished metal, bespoke ironmongery, designer-supplied fabric and matched veneer are common candidates, and the glance table says why.

Can I order before the main contract is signed?

It depends on the route and the contract. Where the client or an agent places orders, items can be bought ahead of the main contract. Inside a contractor’s package, early orders are possible if the contract provides for them: the RIBA Overview describes packages let earlier in Stage 4 under management contracting, and a pre-contract services agreement under which some work can start before the contract sum is settled. Ask the project’s contract adviser.

What must be approved before an early order?

At least the shop drawing, at a named revision, and the control sample. Add the site survey where the item is fitted, the evidence requirements, the quantity, the delivery and storage arrangements, and the authority to commit. The gate table sets them out.

How do I work out the latest order date without a lead time?

Work backwards from the date needed on site: take away the delivery window, the making period and the approvals still to come, each as the maker gives it with the event it is counted from, and keep some float. Where no maker has given a period, write ‘ask’, not an estimate.

Does Make Bespoke Studio order long-lead items before approval?

Our lead times page says we flag long-lead components in the first programme so that they are ordered against drawing approval, and that the clock runs from written approval of the shop drawings and samples. What an early order needs, including any deposit, is agreed with us for each commission, and this sheet states no terms.

Download the factsheet

A two-page A4 PDF with the three-question test, the long-lead register template, the latest-order-date sum and wording for tender documents, to keep with your project file.

Factsheet TL-SPE-24 v1.0 (PDF)