At a glance

Type of changeSample sign-offFire evidenceCertificates, claims and declarationsWarranty, care and drawings
Finish (colour, sheen, process)Re-sign. A new process or finish is a new sample.Check, if part of a classified build-up.Check: emissions data, any EPD.Check: finish warranty, care.
Veneer or solid timber (species, cut, supplier)Re-sign. Approve a range.Check, if the panel is classified.Re-check: certificate code and claim.Check: movement, sizes.
Board or core (MDF, ply, fire-retardant)Check: a finish on another board proves little.Re-check. A class applies to the build-up as tested.Re-check: declaration of performance, emissions, timber claim.Check: thickness, fixings, weight.
Upholstery cover (fabric, leather)Re-sign: colour, pattern, handle.New test. Any change but a simple colour change is a new composite.Check: abrasion, cleaning data, label.Check: care code, yardage.
Foam, filling, interlinerRepeat the sit test.New test. New filling or component supplier is a new composite.Check: feather and emission declarations.Check: build-up drawing, seat warranty.
Hardware (hinges, runners, locks)Re-sign if it shows.Check: a fire-rated door certificate lists tested parts.Not usually affected.Check: load class, cut-outs.
Metal (alloy, plating, finisher)Re-sign: new batch or process.Not usually affected.Check: mill certificate, coating data.Check: corrosion warranty, thickness.
Luminaire parts (driver, LED, glass)Re-sign colour temperature on a mock-up.Not usually affected.Re-check: conformity marking, test records.Check: dimming, warranty.

Re-sign: a new sample or signature. New test: the evidence is void until a new report is issued. Re-check: ask for the new certificate, claim or declaration. Check: confirm in writing. Practice guidance, not a standard: see Sources and caveats.

The test is the evidence, not the look

“Or equivalent” is a judgement about appearance and price. The question that decides what must be redone is a different one: what evidence points at the item? A fire test report names a cover, an interliner and a filling. A chain-of-custody claim belongs to a supplier. An EPD names a product. A sample signature names a batch, a finish and a process. Change the item and each of those stops describing what you receive, however alike the new one looks.

Our own process works the way a register wants it to. In our how we work and pricing pages, a package that comes back over budget is shown with the as-drawn price beside the alternatives, so the design team decides what changes, not the maker, and we agree every change before anything is cut. A change after approval is costed and approved in writing before work changes. The register is the record of that.

What can change without re-approval? Very little. Only tier A in the table below, and only where the specification lists the item as the maker’s choice, so that the list is agreed rather than assumed. Everything else needs the designer’s written approval, and anything that carries evidence needs that evidence re-checked first.

TierWhat it coversWho decidesWhat is recorded
A Record onlyA change to something that no drawing, schedule, sample, report, certificate, claim or warranty names, and that the specification lists as the maker’s choice. Examples to agree, not assume: [concealed fixings of the same type and rating], [the order of assembly and the jigs used].The maker, who tells the designer.One line on the register.
B Approve in writingAnything on the drawing, the schedule or a signed sample with no evidence pointing at it: a visible finish, a handle, a species, a size.The designer, and the client where the finish or the budget is theirs.A register entry, a revised drawing, and a new sample if it shows.
C Re-check the evidenceAnything a report, certificate, claim, declaration or warranty names.The designer, after the new evidence has been checked.A register entry that cites the new evidence, filed with it.
Substitution decision flow: three outcomes, decided by what evidence points at the itemA flow from left to right. A change is proposed. Question 1: is the item on the drawing, the schedule or a signed sample? If no, outcome A, record only, which applies only if the specification lists the item as the maker's choice. If yes, question 2: does any report, certificate, claim, declaration or warranty name it? If no, outcome B, approve in writing: the designer signs, with a new sample if the change is visible. If yes, outcome C, re-check the evidence: a new report, claim or declaration is supplied before use, and then the designer signs.ChangeproposedIs the item on thedrawing, scheduleor a signed sample?YesDoes a report,certificate, claim orwarranty name it?NoA Record onlyOnly if the specification liststhe item as maker's choiceNoYesB Approve in writingDesigner signs; a newsample if it showsC Re-check evidenceNew report, claim ordeclaration before use;then designer signs“Equal” in look is not equal in evidence: the question is what paperwork points at the item.
Substitution decision flow: three outcomes, decided by what evidence points at the item. Original drawing by Make Bespoke Studio.

What each kind of change puts back in question

The table at the top is the summary. Four of its lines rest on documents we read.

Upholstery fire tests. The FIRA and British Furniture Confederation guide says test data applies to the item evaluated, not to the item later supplied. It says a basic alteration to a specification makes a new model that must be re-tested: a change of cover other than a simple colour change, of pattern or construction other than minor changes, of filling, or of component supplier. It adds that enforcement authorities normally expect a UKAS-accredited test certificate no more than a year old, and less for larger runs. That is what it says they expect, not a legal limit. See BS 7176 hazard categories and the fire documentation matrix.

Wall linings and panelling. Approved Document B volume 2 (England, buildings other than dwellings) says test evidence for a fire classification should be checked to see that it applies to the intended use, and that small differences in detail, such as fixing method, joints, dimensions and air gaps, might significantly affect performance and should be tested or assessed. It also says a reaction-to-fire classification is valid only when the product is fixed to a substrate of the kind it was tested on. So a change of board behind a veneer, of adhesive or of fixing is a change to the evidence. It is guidance to the Building Regulations: the fire consultant and building control decide what applies.

Timber claims. FSC UK’s buyer checklist looks for six things on delivery documents: the date, supplier and customer details, a product description, the quantity, the supplier’s certificate code and the FSC claim. A new supplier has a new code, and a move from FSC 100% to FSC Mix is a different claim. See specifying FSC and PEFC.

EPDs. An EPD covers the products it names. In the International EPD System an updated EPD is re-verified, and a substantial change to a product, meaning a different function or different major manufacturing steps, leads to the old EPD being withdrawn and possibly to a new one. So the EPD of the original does not carry over to a substitute: see how to read an EPD.

Samples. A change of material batch, supplier, process or finish after approval is a new sample and a new signature: see the sample hierarchy sheet. For a visible change to a room or a repeated item, a mock-up may need to be shown again.

The register: one line per proposed change

Keep one register for the project, beside the drawing register, and give each line a reference that is never reused. Anyone may raise a line. The designer decides. The columns below are a starting point, filled in here with two invented examples.

RefItem and changeReason, and who proposedEffect on look and functionEvidence affectedNeeded before useProgramme and cost effectDecision, name, date
R-01W-03 wall unit doors. Finish F-02 satin lacquer to [semi-gloss], same colour reference.[Maker], to suit the spray programme.Sheen shows. Colour to be checked under [named light].Control sample S-01 and its viewing record.New control sample signed. S-01 marked superseded.[Maker states working days]. Cost: [line in revised quotation, ref].Approved with conditions: [designer], [date].
R-02B-01 banquette seat. Cover [fabric ref A] to [fabric ref B].[Designer], to meet the budget.Pattern scale and handle differ.BS 7176 composite report; abrasion data; label.New composite report for cover, interliner and filling together; new sample.[Maker states working days]. Cost: [line in revised quotation, ref].Pending: [designer], [date].
R-03
  • Raise it before ordering. The line is approved, approved with conditions, refused or withdrawn before the item is ordered, not after it arrives.
  • State the effect on time and cost as the maker’s own figure, in a revised quotation line, never in the register by assumption. This sheet gives no prices.
  • Update the paperwork. A change that is approved goes onto a new drawing revision, the FF&E schedule and the sample register. The superseded sample is marked so.
  • A change that moves the price or the programme is also a variation, and follows the written variation route in your contract.
  • File the new evidence with the line, so that the project file shows what was checked, by whom and when.

Value engineering, without erosion

Our value engineering article sets the order: state the design intent first and agree what must not change, then look for the smarter route. The register fits that order. Put the things that must not change at the top of the specification, price the as-drawn version and the alternatives as separate options, as the quote comparison sheet advises, let the designer choose, and then log each chosen change.

Count the whole saving. A swap that needs a new composite test, a new sample or a new certificate has time and cost of its own. Ask the maker to state them in the revised quotation, so the design team sees the net effect, not just the headline.

Define “or equivalent” or do not use it. If the specification allows equivalents, say what the term means: the same appearance as signed sample [S-nn], the same sizes within the stated tolerance, the same published performance data, the same kind and standard of evidence, and a named supplier. An item that meets those points still goes through the register, as an alternative offered separately with its data sheet. This is the gate the joinery specification sheet describes.

Specification wording

Paste into your schedule or specification and replace anything in [square brackets] with your own figures. Wording is a starting point: your specification governs.

No substitution without written approval
No substitution, alternative or 'equivalent' for any item, material, finish, component or supplier named in the drawings, specification, FF&E schedule or approved samples is to be made without the written approval of [designer], given on substitution register [ref] before the item is ordered. The proposer states the reason, the effect on appearance and function, the evidence that names the original (test reports, certificates, claims, declarations, warranty), what will replace it, and the effect on programme and contract sum as stated in the maker's revised quotation. 'Equivalent' means an item approved under this clause, not an item the supplier judges equivalent.
Evidence for a substituted item
A substituted item is not approved until the supplier provides evidence of the same kind and standard as for the item it replaces: [a test report for the new upholstery composite, from a UKAS-accredited laboratory, dated within [12] months] [the supplier's certificate code and claim on the delivery document] [a declaration of performance and emissions class] [an EPD to the same PCR, in date] [warranty terms]. Where that evidence cannot be supplied, the substitution is refused.
Maker's choice list
[Maker] may change the following without prior approval, if the register is updated and the item is named in no approved sample, report, certificate, claim or declaration: [concealed fixings of the same type and rating]; [assembly sequence and jigs]; [ ]. Everything not listed needs approval.
Unapproved changes
Work that departs from an approved item without written approval on the register may be rejected. [Remedy, and who bears the cost of removal, replacement and re-testing, to be agreed with the project's contract adviser.] Approved changes are made by new drawing revision and, where they move the price or programme, by written variation.

Terms used on this page

Value engineering
A structured review of a design to cut cost without losing the function or performance the client needs. Done badly it swaps materials and quietly drops compliance evidence, so each change should be recorded and re-approved.
Variation order
A written instruction to change what was agreed after the contract or sign-off, stating the effect on price and time. Verbal changes to items already ordered are a common source of dispute.
Upholstery composite
The exact combination of cover, interliner and filling that was tested together. A fire certificate only applies to that combination, so changing the foam or cover can make it invalid.

All specification and delivery terms

Standards and sources

Questions we are asked

Can the maker swap a board for an equivalent one?

Not without the designer’s written approval, and not before the evidence has been re-checked. A board can carry a declaration of performance, an emissions class, a timber claim and a fire class that applies to the finished build-up. A look-alike board has none of them until the supplier shows it does.

Does changing the fabric colour need a new fire test?

The FIRA and BFC guide says a change of cover other than a simple change of colour makes a new model that must be re-tested, so a plain colour change is the exception. Confirm with the test house that a dye change does not alter the back-coating or any treatment, and ask for it in writing.

Does a cheaper timber or veneer need re-approval?

Yes. A different species, cut, flitch or supplier needs a new sample, which for natural materials should show a range, and a new certificate code and claim from the supplier if timber claims are specified.

Who pays for re-testing or a new sample?

The contract decides, and this sheet gives no prices. Ask the maker to state the cost and the time of any re-test, new sample or new certificate as a line in the revised quotation before the change is approved, so the net saving is visible.

Does value engineering mean cheaper?

Not necessarily. Our article describes it as protecting the design intent and finding a smarter route to the rest, and notes that durability is value. Some changes cost the same and last longer. The register records them all the same way.

How do I avoid “or equivalent” taking over?

Say what it means in the specification, require the alternative to be offered separately with its data sheet and a sample, and approve it on the register before the order is placed. Without that, the supplier decides what counts as equivalent.

Is a substitution the same as a variation?

Not quite. A substitution is a change to what is specified, and the register records it. A variation is the contractual instruction that changes price or programme. A substitution that moves either is also a variation.

Download the factsheet

A two-page A4 PDF with the table of what each change puts back in question, the decision flow and the clause wording, to keep with your project file.

Factsheet TL-SPE-18 v1.0 (PDF)