At a glance
| Group | Columns | It answers | Links to |
|---|---|---|---|
| Identity | Item code, room or area, item, quantity, drawing ref | What is it, and where does it go? | Drawing register |
| Specification | Description, finished size, materials, finish ref, sample ref, COM details | What exactly is to be supplied? | Finishes schedule and samples |
| Commercial | Supplier, quote ref, price basis, unit cost, budget line | Who supplies it, and on what basis? | Quotations |
| Procurement | Status, PO ref, order date, needed on site, delivery to | Where is it in the buying process? | Purchase orders and programme |
| Compliance | Fire regime, hazard category, fire standard, composite ref, test report ref, report date, label fitted, timber claim, certificate no., other evidence, checked by and date | What evidence shows it meets the brief? | Certificate file |
| Approval | Shop drawing, sample status, revision, change note | What was approved, and what changed? | Approvals log |
Thirty-six columns in all. Use only the columns your project needs, but keep the compliance group: a blank cell cannot be told from a forgotten one.
The schedule is an index
An FF&E schedule is a line-by-line list of every furnishing item on a project, used to specify, price, order and track the items. It does not replace the drawings, the finishes schedule, the quotations, the purchase orders or the certificates. It points to them. Each group of columns on the drawing below indexes one document, so that anyone reading a row can find the evidence behind it.
The grouping is simple. Identity says what the item is and where it goes. Specification says exactly what is to be supplied. Commercial and procurement say who supplies it and where it is in the buying process. Approval records what has been signed off. Compliance, highlighted on the drawing, records the evidence that the item meets the brief.
The columns, one by one
Copy the column names into a spreadsheet, one row per item and finish variant. Example entries are in square brackets for you to replace. A spreadsheet version of this template could follow.
| Column | What to enter | Example (replace) |
|---|---|---|
| Identity | ||
| Item code | A unique code for the item and its finish variant. Never reused. | [B-01] |
| Room or area | Where it goes, using the room names on the drawings. | [Restaurant, main dining] |
| Item | A plain name for the piece. | [Banquette seating, bespoke] |
| Quantity | Identical items, plus any spares agreed. | [ ] plus [ ] spare |
| Drawing ref | The drawing number and revision that shows it. | [A-210 rev C] |
| Specification | ||
| Description | One line, in the wording of the closed specification. | [Species, cut, board, finish, hardware] |
| Finished size | Width, depth and height in mm as finished, with the word “finished”. | [W x D x H] mm finished |
| Materials | Timber species and cut, board, veneer, filling, cover, metal. | [ ] |
| Finish ref | The code in the finishes schedule. | [F-03] |
| Sample ref | The approved sample the item is to match. | [S-02] |
| COM details | Where the designer supplies fabric or leather: reference, width, quantity, batch. | [Fabric ref, width, batch] |
| Commercial | ||
| Supplier | The maker or supplier who has quoted. | [Name] |
| Quote ref | Quotation number and date. | [ ] |
| Price basis | What the price covers: made only, delivered, delivered and installed. | [Delivered and installed] |
| Unit cost | Cost per item, in the currency stated. | [ ] |
| Budget line | The budget line it is charged to. | [ ] |
| Procurement | ||
| Status | One value from a fixed list: specified, quoted, approved, ordered, in production, delivered, installed, snagged, accepted. | [Approved] |
| PO ref | The purchase order number. | [ ] |
| Order date | The date the order was released. | [ ] |
| Needed on site | The date the item is needed in the room, from the programme. | [ ] |
| Delivery to | Address, floor and access point. | [ ] |
| Approval | ||
| Shop drawing | Drawing number and status: submitted, approved, approved as noted, or revise and resubmit. | [A-210 rev C, approved as noted] |
| Sample status | Sample reference and the date it was approved. | [S-02, date] |
| Revision | The schedule revision at which this row last changed. | [Rev D] |
| Change note | What changed, and the variation reference. | [ ] |
The compliance columns
Most schedule templates stop at a single field for fire rating. For a UK project that is not enough, because the evidence differs by item and the rules differ by building. Three points from the sources we have read:
- The regime depends on the building. FIRA’s guide says holiday apartments and houses are covered by the 1988 Regulations and hotels are not: hotel furniture is governed through the fire risk assessment under the Regulatory Reform (Fire Safety) Order 2005. Chalet hotels and similar mixed premises are a grey area, so ask the project’s fire risk assessor.
- A claim is not evidence. FIRA notes there is no formal scheme for proving compliance with a standard, so a supplier can simply claim it. That is why the schedule records a test report reference, its date and who checked it.
- The test belongs to the item tested. Each upholstery composite, meaning cover, interliner and filling together, needs its own test, and test data applies to the item evaluated, not to every item supplied.
| Column | What to enter | Example (replace) |
|---|---|---|
| Fire regime | Which regime applies. The Furniture and Furnishings (Fire) (Safety) Regulations 1988 cover furniture ordinarily intended for private use in a dwelling. For non-domestic premises, the fire risk assessment under the Regulatory Reform (Fire Safety) Order 2005 sets the level. | [Fire risk assessment] |
| Hazard category | For upholstered seating: low, medium, high or very high, as set by the premises’ fire risk assessment, using BS 7176. The standard gives typical examples only. | [From the assessment dated ...] |
| Fire standard | The standard the item is to meet: BS 7176 for upholstered seating, BS 7177 for mattresses, BS 5867-2 for curtains and drapes, with the ignition source where one is given (BS 5852). | [BS 7176] |
| Composite ref | The upholstery composite: cover, any interliner and the filling, which are tested together. Each composite needs its own test. | [Cover ref + interliner + filling ref] |
| Test report ref | The report for that composite. FIRA says enforcement officers normally expect a UKAS-accredited certificate no more than 1 year old. | [Report ref, laboratory] |
| Report date | The date on the report, so its age can be seen at a glance. | [ ] |
| Label fitted | Whether the permanent label is on the item. BS 7176 calls for one on each item for full compliance. | [Yes / no / n/a] |
| Timber claim | The certification claim for each timber item: FSC 100%, FSC Mix, FSC Recycled, PEFC, or none. | [FSC Mix] |
| Certificate no. | The supplier’s chain-of-custody certificate number as shown on the delivery documents, checked against the certification body’s database. | [ ] |
| Other evidence | Any further evidence the brief asks for: an environmental product declaration, a chemical or emissions declaration, a declaration of performance for boards. | [Only if required] |
| Checked by, date | Who matched the evidence to the item, and when. | [Initials, date] |
Tip: never leave a compliance cell blank. Write n/a and the reason, so that a blank can only mean a missed item.
Worked rows
The same columns filled in, as placeholders, for a banquette and a brass-inlaid cabinet. The cabinet row shows how to record a column that does not apply: say so and say why.
| Group | Bespoke banquette (example) | Bespoke brass-inlaid cabinet (example) |
|---|---|---|
| Identity | [B-01], [Restaurant, main dining], banquette seating, [quantity], [A-210 rev C] | [C-04], [Reception], console cabinet with brass inlay, [quantity], [A-305 rev B] |
| Specification | [W x D x H] mm finished; solid [species] frame; [foam and filling]; [leather ref]; finish [F-03]; sample [S-02] | [W x D x H] mm finished; [species] veneer on [board] with solid lipping; brass inlay [alloy, thickness]; lacquer [sheen]; finish [F-07]; sample [S-05] |
| Commercial | [Supplier]; [quote ref]; [delivered and installed]; [unit cost]; [budget line] | [Supplier]; [quote ref]; [delivered and installed]; [unit cost]; [budget line] |
| Procurement | Status [approved]; PO [ref]; ordered [date]; needed on site [date]; delivery to [address, floor] | Status [quoted]; PO [ref]; ordered [date]; needed on site [date]; delivery to [address, floor] |
| Compliance | Regime [fire risk assessment]; hazard [from the assessment]; standard [BS 7176]; composite [cover + interliner + filling]; report [ref, date]; label [yes]; timber [FSC Mix, certificate no.]; checked [initials, date] | Regime [n/a, say why]; fire standard [n/a unless the fire risk assessment asks]; timber [PEFC, certificate no.]; other evidence [n/a, say why]; checked [initials, date] |
| Approval | Shop drawing [A-210 rev C, approved as noted]; sample [S-02, date]; revision [D] | Shop drawing [A-305 rev B, submitted]; sample [S-05, date]; revision [D] |
Rules that keep the schedule honest
- One row per item and finish variant, with a unique item code that is never reused.
- One status list, fixed at the start, so that a filter means the same to everyone.
- One revision letter per issue, with the change note recording what moved.
- Every cell completed. Use n/a and the reason, never an empty cell.
- Evidence lives in files, not in the cell. The cell holds the reference; the certificate sits in the certificate file.
- The schedule is an index, not a compliance record. The certificates, the test reports and the fire risk assessment are the record.
Specification wording
Paste into your schedule or specification and replace anything in [square brackets] with your own figures. Wording is a starting point: your specification governs.
The FF&E schedule is issued as revision [letter] and held by [party]. One row per item and finish variant; item codes are unique and never reused. Every cell is completed: write n/a and the reason, not a blank. Status is one of: specified, quoted, approved, ordered, in production, delivered, installed, snagged, accepted.
Finished size: width x depth x height in mm as finished. Finish ref: the code in the finishes schedule [reference]. Sample ref: the approved sample [S-nn] the item is to match. COM details: where [designer] supplies fabric or leather, its reference, width, quantity and batch, with its fire test evidence.
Fire regime: [fire risk assessment under the Regulatory Reform (Fire Safety) Order 2005 / Furniture and Furnishings (Fire) (Safety) Regulations 1988]. Hazard category: [low / medium / high / very high] as set by the fire risk assessment dated [date]. Fire standard: [BS 7176 / BS 7177 / BS 5867-2]. Composite ref: cover, interliner and filling tested together; a different composite needs its own test. Test report: [UKAS-accredited, no more than 1 year old], reference and date. Label fitted: [yes / no / n/a].
Timber claim: [FSC 100% / FSC Mix / FSC Recycled / PEFC / none] for each timber item. Certificate no.: the supplier's chain-of-custody certificate number as shown on the delivery documents, checked against the certification body's database by [name] on [date]. Other evidence: [environmental product declaration / chemical or emissions declaration / declaration of performance], only where the brief requires. Checked by, date: [initials, date].
Shop drawing: drawing number and status [submitted / approved / approved as noted / revise and resubmit]. Sample status: sample ref and date approved. Revision: schedule revision at which the row last changed. Change note: what changed, and the variation reference.
Terms used on this page
- Upholstery composite
- The outer cover, any interliner and the filling of a seat, tested together. Each different composite needs its own passing test.
- Hazard category (BS 7176)
- The level of ignition resistance expected of upholstered seating: low, medium, high or very high. The fire risk assessment decides it; the standard gives typical examples.
Standards and sources
- FIRA: Fire safety of furniture and furnishings, non-domestic sector (2010 edition): read via a hosted copy on 5 Nov 2026; check FIRA for the current edition.
- Furniture and Furnishings (Fire) (Safety) Regulations 1988, regulation 3: page read 5 Nov 2026.
- FSC UK: Choose FSC and Is it FSC? buyer guides: delivery-document checks and claim types (page dated 7 Jul 2026).
- Make Bespoke Studio journal: Hotel FF&E explained: what FF&E covers.
Questions we are asked
What is an FF&E schedule?
A line-by-line list of every furnishing item on a project, with its code, room, description, finish, size, supplier, quantity and status, used to specify, price, order and track the items. The most useful versions also record compliance evidence.
What columns should an FF&E schedule have?
Six groups: identity (code, room, item, quantity, drawing reference), specification (description, finished size, materials, finish and sample references), commercial (supplier, quote, price basis), procurement (status, order, dates, delivery), compliance (fire, timber and test evidence) and approval (shop drawing, sample, revision, change).
What is the difference between an FF&E schedule and a finishes schedule?
A finishes schedule lists the surface finishes, colours and materials in each space and cross-refers to samples. An FF&E schedule lists the items. The FF&E schedule should reference the finishes schedule rather than repeat it.
Do hotels and holiday lets follow the same fire rules for furniture?
Not under the guidance we have read. FIRA’s guide says holiday apartments and houses are covered by the 1988 Regulations, while hotels are covered by the fire risk assessment under the Regulatory Reform (Fire Safety) Order 2005. Mixed premises are a grey area, so confirm with the project’s fire risk assessor. The fire regime column records which applies.
Is an FF&E schedule a compliance record?
No. The schedule is an index. The certificates, the test reports and the fire risk assessment are the record, and the schedule holds the references that lead to them.
Download the factsheet