At a glance

ClassWhat it meansExamples (they vary by material)Remedy window to agree
Class A
Safety or function
Unsafe, or does not work as intended.A loose or failing fixing; a wobbling seat or table; a drawer or door that jams; a sharp edge or proud fixing.Shortest. Attend promptly; out of use until safe.
Class B
Off specification
Fails the drawing, specification, control sample or a stated tolerance, seen under the agreed conditions.Wrong finish or sheen against the control sample; wrong material or hardware; a size outside tolerance; a visible chip, scratch or dent.Repair or replace, by an agreed date.
Class C
Adjustment or finishing
Within specification, but needs adjusting, finishing or cleaning.A door or drawer to realign; a hinge to adjust; a small touch-in not visible under the agreed conditions; final clean.Usually the same visit or the next.
Not a defect
Natural variation
A feature the approved sample, range or specification allows.Grain, figure and colour variation within the approved range; natural marks in leather within the agreed grade.None. Record it as accepted.
Damage by othersDamage after the recorded condition, once handed to others.A scratch from a following trade; a stain from another trade’s product; a knock during fit-out.Off the snag list. Who pays is a contract matter.
Variation
A change, not a snag
Built as drawn, but now wanted differently.A different handle, an extra shelf, a new finish.Priced and approved in writing first.

Classes and windows are examples to agree in the project documents, not a standard.

Agree the criteria before the work is made

Snagging is checking finished work against the drawings, the specification and the approved samples, and listing what does not comply. Stone Federation GB, writing about natural stone, makes two points that apply well beyond stone. There are no specific standards for snagging or for what is acceptable, and quality is a matter of personal judgement, which is why it causes friction between designer, contractor, maker and client. We found no snagging standard for joinery or furniture either.

The remedy is to settle the criteria while nothing has been made. Write them into the specification, tie them to the signed control sample and the approved range, and fix how you will inspect. The inspection then applies what was agreed and adds nothing new. The drawing shows where the criteria are written and where they are used.

Snagging timeline: the criteria are agreed first and applied at the inspectionSeven steps in a row: specification and drawings, control sample, first article, delivery and fitting, joint inspection, remedy and re-inspection, and the acceptance record. Brackets group them into three phases: agree the criteria (the first two steps), make and check (the next two) and inspect and accept (the last three). The first phase is shaded green because that is where the criteria for what counts as a defect are written.Agree the criteriaSpec anddrawingsControlsampleMake and checkFirstarticleDeliveryand fittingInspect and acceptJointinspectionRemedy,re-inspectAcceptancerecordWritten here:benchmark, tolerances,range, conditions, classesApplied here:the inspection uses what was agreed, and nothing new
The criteria are written in the first phase and only applied in the last. Original drawing by Make Bespoke Studio.

What to settle before production

  • The benchmark. Drawings and revision, specification clauses, signed control samples and the approved range. See the sample hierarchy sheet.
  • Tolerances, for the maker and for the site. Manufacturing and site tolerances are different things, so agree both. Measure them against the stated figure; do not borrow a number from a general guide. See the sheets on joinery tolerances and furniture tolerances.
  • Natural variation. What is accepted for each material, written down or shown in a range.
  • Inspection conditions. Light, distance, angle, and who attends.
  • Classes and remedy windows. The table at the top of this page is a starting point.
  • Timing. When the inspection happens, and what must be finished first, including site readiness. See the site-readiness checklist.
  • Who decides a disputed item, and how that decision is recorded.

Payment is a separate question. Payment and retention are contract matters. Stone Federation GB’s guide says the inspection and snagging process should not be linked to the release of payment, and that the contract should ideally say so. This sheet gives no legal advice: take advice from your contract adviser before writing payment terms around snagging.

Classify what you find, in order

Not every finding is a defect, and not every defect is equal. Sorting before arguing keeps an inspection fair. The questions below put a finding into one class, in order. Natural variation and damage by others are settled first, because neither is a defect in the work. The split between safety or function and appearance follows the one Stone Federation GB uses, with appearance divided into what fails the specification and what only needs finishing.

Classifying a snagging finding: four questions in orderA row of four question boxes. First: is the finding shown in the drawing, specification, control sample or approved range? If yes, it is not a snag: record it and move on. Second: did it happen after the recorded handover condition? If yes, it is damage by others and is listed separately. Third: is it unsafe, or does it not work? If yes, it is Class A. Fourth: does it fail the specification, sample or a tolerance, seen under the agreed conditions? If yes, it is Class B. If no, it is Class C: adjust, finish or touch in.Something looks wrong. Ask these in order:In the drawing,spec, controlsample or range?YesNot a snag.Record it,move onNoDid it happenafter therecorded handovercondition?YesDamage byothers. Listit apartNoIs it unsafe, ordoes it not workas intended?YesClass A:safety orfunctionNoFails spec, sampleor tolerance, seenunder the agreedconditions?YesClass B:off specificationNoClass C:adjust, finishor touch inCompare with the written criteria, not with taste. Classes and windows are examples to agree.
Four questions, asked in order, put a finding into a class. Original drawing by Make Bespoke Studio.

Natural variation by material

The hardest calls are appearance calls on natural materials. The table gives examples of what is usually expected and what is usually a defect. They are examples to adapt: the project’s own samples and range decide, and the partner workshops should say what they treat as natural for each finish.

MaterialExpect and accept, within the approved rangeTreat as a defectCompare with
Solid timberColour and grain differences between boards, and features the grade allows, as the control sample shows.Splits, loose or dropped knots, tear-out, sapwood where the specification excludes it, boards that have cupped or bowed beyond the agreed tolerance.Control sample, grade clause, tolerance clause.
VeneerFigure and colour varying from leaf to leaf within the approved flitch, matched as the layout drawing shows.A match different from the layout, bubbling or lifting, an unagreed patch or repair, a sanded-through leaf.Layout drawing and flitch sample.
Lacquer or paintSlight differences in sheen with the viewing angle on large surfaces, within the sample range.Runs, sags, dust, thin or patchy areas, a colour or sheen visibly different from the control sample, chipped edges.Finish control sample, viewed under the agreed conditions.
Metal and patinaHand-applied patina or brushed finish varying slightly between pieces, as the finish sample shows.Scratches or dents, weld marks where a finished weld is specified, a patchy or flaking coating.Finish sample.
StoneVeining, fills and natural pits that are typical of the stone and listed in the range report.Chips, cracks, saw or polishing marks on a visible face, ragged edges to joints or edges.Range report and stone sample.
Leather and fabricNatural marks, grain and shade differences between hides or rolls, within the agreed sample range.Skipped or broken stitching, a torn or marked cover, wrinkles or puckering the mock-up did not show, pattern out of line where a layout was agreed.Control sample, mock-up, layout drawing.

Inspect fairly, record, close out

Conditions to agree and write down, with the points Stone Federation GB makes for stone that carry over:

  • Measure what can be measured. Joints, levels, squareness and flatness can be checked against the stated tolerance, which is a matter of fact. Appearance is judged by eye, under the agreed conditions, against the control sample.
  • Light and distance. Agree and record them. For stone, Stone Federation GB cites 2 m for approving samples. For installed stone in a small room it accepts viewing from the middle of the room, no closer than 1 m, in daylight where possible with wall lights and downlights off, and not with torches or site lamps. Those figures are for stone: agree your own for joinery and furniture.
  • Who attends. The person who approved the samples should take part in the final inspection, so that the benchmark is not reinterpreted late.
  • Timing. Inspect after the maker or installer has done its own check and cleared its own snags, and after other trades have finished in the area. If an earlier inspection is unavoidable, record the condition with photographs so that later damage is not blamed on the work.
  • Photographs. Photograph each issue at normal magnification with a scale or reference object in shot, as well as a wider view.

Then work the list in a fixed order: the maker’s own check, a joint inspection, each item recorded and classed, an owner and a window agreed, the remedy, a re-inspection of the listed items only, and an acceptance record signed by both sides. Record each item the same way:

FieldWhat to put
Reference and locationA running number, the room and the item code from the FF&E schedule.
FindingWhat is wrong, and which document it fails: drawing, clause, control sample, tolerance.
ClassA, B or C, or “not a defect” or “damage by others” with the reason.
PhotographA reference to a photograph at normal magnification with a scale in shot, plus a wider view for position.
Action and ownerWhat will be done, and by whom.
Due dateFrom the remedy window agreed for the class.
Re-inspectedDate and initials, and the result.

Damage by others, and sign-off

Record the condition. Before protection goes on, or before the piece is handed to other trades, inspect jointly and photograph the work. Stone Federation GB advises that this record is the baseline: damage after it is treated as damage by others, and is dealt with separately from the snag list. Who pays for it is a matter for the contract.

Sign off. When the agreed classes are closed, sign an acceptance record that says who accepted, when, and what remains open. A new item raised after sign-off is assessed on its own: is it a defect, wear, or damage? The length of any snagging or defects period after handover is agreed in the contract or the commission. The studio’s own process is described on the installation and aftercare pages.

Specification wording

Paste into your schedule or specification and replace anything in [square brackets] with your own figures. Wording is a starting point: your specification governs.

Acceptance basis
Work is accepted against drawings [numbers, revision], specification clauses [numbers], approved control samples [S-01 to S-nn] and [the range report / range samples]. Natural variation within the approved range is not a defect. A feature none of these covers is referred to [designer], and the decision is recorded.
Inspection conditions
Joint inspection by [designer], [maker or installer] and [contractor / client], on a date agreed [number] working days ahead, after the maker's own check and after other trades have finished in the area. [Person who approved the samples] attends. Appearance is judged from [distance] m in [daylight / the room's lighting]; no torches or site lamps. Dimensions and alignment are measured against the stated tolerances.
Defect classes and remedy windows
Class A (unsafe or does not work): attended within [number] working days; out of use until safe. Class B (fails the specification, sample or a stated tolerance): repaired or replaced within [number] working days or by a date agreed. Class C (adjustment or finishing): completed within [number] working days. Natural variation within the approved range, and damage by others, are not defects.
Recording and re-inspection
Each item is recorded with location, item code, finding, class, a photograph with a scale, action owner and due date. Re-inspection covers the listed items only. An item is closed when [designer] confirms in writing.
Damage by others and acceptance
The condition of the work is recorded jointly, with photographs, on [date / before protection is applied]. Later damage is listed separately as damage by others. Acceptance is recorded on [form], signed by [designer] and [maker or installer], when all Class A and B items are closed [and Class C items are closed or agreed]. Payment and retention are governed by [contract clause], which this clause does not alter.

Terms used on this page

Snagging
Checking finished work against the drawings, specification and approved samples and listing what does not comply or does not work. There is no formal snagging standard, so criteria need to be agreed up front.
Natural variation
Differences in colour, grain, figure or texture that belong to the material and fall within the approved sample or range. They are accepted, and recorded as accepted, rather than snagged.
Damage by others
Damage that happens after the condition of the work was recorded and it was handed to others, such as a following trade. It is listed apart from the snag list; who pays is a contract matter.

All specification and delivery terms

Standards and sources

Questions we are asked

What is the difference between a snag and a defect?

The words overlap and contracts differ. Stone Federation GB describes snagging items as those that need attention but are not significant enough to delay practical completion. A defect is more generally any work that does not comply with the contract. Agree the terms, and the classes, in writing.

When should acceptance criteria be agreed?

Before the work is made: in the specification, the signed control samples, the approved range and the inspection conditions. Criteria written after the work is delivered are argued from opinion.

How do I tell natural variation from a defect?

Compare the item with the control sample and the approved range, under the agreed light and distance. A feature the sample or range allows is natural variation. A feature that neither covers is referred to the person who approved the samples, and the decision is recorded.

Who should attend the snagging inspection?

The designer, the maker or installer, and the contractor or client as the contract requires. Stone Federation GB recommends continuity: the person who approved the material at design stage should take part in the final inspection.

Is there a standard for snagging bespoke joinery or furniture?

We did not find one. Stone Federation GB notes that there are no specific standards for snagging, and points to NHBC guidance on finishes for housing, which we could not open. Agree the criteria in the project documents.

What is damage by others?

Damage that happens after the condition of the work was recorded and it was handed over, for example by a following trade. Recording the condition jointly, with photographs, before protection goes on is what lets it be separated from a snag.